Заради подобро корисничко искуство нашата веб страна, mer.com.mk користи ?колачи?а“ (eng. "cookies"). Со понатамошно користе?е на веб-страницата, се сложувате со користе?е на колачи?ата. Детални информации за Веб колачи?ата "Cookies“ можете да на?дете во нашиот документ за Политика за користе?е Web колачи?а
CONTACT: +389 2 609 0137 | contact@mer.com.mk
According to the Law on borrowing by the Republic of North Macedonia from Deutsche Bank and Erste Bank under the Facility Agreement for the Project “Gasification of the Republic of North Macedonia – Phase 1 section Stip – Negotino - Bitola and section Skopje – Tetovo – Gostivar”, funds for the construction of section “Valve Station 5 (Stip) - Negotino” have been provided.
The construction began in June 2016 and is expected to be completed in May 2019.
Technical parameters:
The route of “Valve station 5 (Stip) – Negotino” starts from Valve Station 5 near the city of Stip (where the section “Klechovce-Valve station 5” ends), passes the Serta mountain, passes through the far eastern part of the Krivolak military range and goes towards the Vardar river. After the crossing on the Vardar river, the main gas pipeline section until its end at the connection for Kavadarci is moving west. In this part, the route goes south from Negotino, north of TPP Negotino and north of the city of Kavadarci.